Summit Cove Loop Project Blog

Updates on construction, project milestones, public meetings and opportunities for input.

Sign Up Today!
Go to our electronic notifications menu to sign up for Summit Cove Loop Blog posts via email.

View All Posts

Jul 13

Culvert work complete

Posted on July 13, 2017 at 5:20 PM by Julie Sutor

Over the past few days, crews have replaced old culverts and installed two new ones underneath Cove Boulevard to improve drainage in several locations. A big thanks to everyone in the neighborhood for driving cautiously through the work zone and paying close attention to the flaggers.

Next week, crews will be milling the existing asphalt in both lanes of Cove Boulevard, from Whispering Pines Ranch Road to the north entrance of Summit Cove Elementary. The asphalt will be recycled in place to serve as subgrade in preparation for a new surface. Expect single-lane closures, and stay alert for flaggers. Both lanes will be open at the end of each construction day.