Jul 27

Road stabilization continues

Posted on July 27, 2017 at 2:50 PM by Julie Sutor

Crews on the Summit Cove Loop Project continued stabilization work this week to build up the widened roadway platform and repair soft spots, delaying the paving until the latter half of next week. Work will also begin next week on the south end of the project in front of the school, where the existing road will be recycled into usable material, just as we did in the first half of this summer's work. 

Please be aware that the trailhead parking across from the school is temporarily closed. Please use the upper parking lot in front of the Summit Cove Elementary School for trail access, and use caution when crossing through the construction zone.

Your County staff and our contractor would like to thank all of the residents and visitors in the neighborhood for your patience and understanding during this construction process and any associated traffic delays.

An excavator works on a road, where the old asphalt has been removed.