Jul 17

July 17 Update

Posted on July 17, 2015 at 4:26 PM by Julie Sutor

Side-Road Repaving
Cutler Repaving is making good progress on the side roads. Work on Glacier Court is finished, as are half of Vail Circle and half of Idlewild Drive. On Monday, July 20, the crew should finish Idlewild Drive, as long as the weather cooperates. On Tuesday, July 21, they will head to Hideaway Court. The remaining sections of Vail Circle will be the last of the side-road repaving work. If we don’t have any significant weather delays, the repaving of side roads will wrap up before the end of the week.

Notably, the crew did experience a delay earlier this week when a car was parked in the roadway. Please be sure to leave the road clear so crews can finish their work.

Summit Drive
Columbine Hills Concrete has not experienced any weather-related delays, and its work is proceeding on schedule. All the culverts that needed replacing have been removed and replaced. During the week of July 20, the crews will do some minor grading and topsoil placement in disturbed areas off the roadway. Residents will see only very minor traffic disruptions along Summit Drive as we allow the repaver to finish work on the side roads.