Summit Cove Loop Project Blog

Updates on construction, project milestones, public meetings and opportunities for input.

Sign Up Today!
Go to our electronic notifications menu to sign up for Summit Cove Loop Blog posts via email.

View All Posts

Aug 21

Aug. 21 Update

Posted on August 21, 2015 at 3:18 PM by Julie Sutor

The final details of Phase 1 of the Summit Cove Loop project are wrapping up. Crews began demobilizing the staging area, and this activity will continue the week Aug. 24. They picked up erosion control logs and spread topsoil in disturbed areas.

Mailboxes
Crews are currently installing mounts for all mailboxes that have been affected by the project, and they expect to finish on Friday or Monday. Installation of the new mailboxes and posts will begin next week, and we hope to have most (if not all) installed by Friday, Aug. 28.

Pavement Marking
Crews are planning to conduct bicycle-pedestrian lane striping and pavement marking on Summit Drive in early September.